Core Scientific Plans $1.3 Billion Texas Data Center Build
A Nov. 13 TDLR entry lists a $1.3 billion Core Scientific data center in Hunt County, Texas, with AMD leasing 110 megawatts ahead of a Sept. 4, 2028 target.

Outputs
$1.3 billion, 341,326-square-foot data center planned at Core Scientific’s Hunt County site
TDLR entry dated Nov. 13 names Telios Quinlan One, LLC as owner and sets Sept. 4, 2028, for completion
AMD leased about 110 megawatts, with initial delivery expected in the first half of 2028
Colocation generated $215.4 million, or about 92%, of third-quarter revenue; Bitcoin mining generated 7.5%
Core Scientific plans to end its own mining operations by Dec. 31, 2026
By Tom Whitfield
A $1.3 billion data center spanning 341,326 square feet is planned at Core Scientific’s Hunt County, Texas, site, according to a Friday, Nov. 13 project entry in the Texas Department of Licensing and Regulation’s records.
The record names Telios Quinlan One, LLC as owner and lists Nov. 24 for the construction start. It sets Sept. 4, 2028, as the project’s completion date.
What does the AMD lease establish?
Advanced Micro Devices has leased about 110 megawatts of capacity at the facility. Initial delivery is expected in the first half of 2028, ahead of the Sept. 4, 2028, completion date.
The lease gives Core Scientific a named customer before the facility reaches full completion. It also advances the company’s shift from Bitcoin mining toward artificial intelligence and high-performance computing hosting.
Core Scientific acquired the Hunt County site in May for $232.5 million in cash. The planned project adds 341,326 square feet of hosting infrastructure to that acquired site.
The entry lists Tuesday, Nov. 24, as the construction start, with completion on Sept. 4, 2028. That gives the company a defined build and delivery window ahead of its post-mining operating plan.
How much does hosting drive revenue?
Core Scientific had 485 megawatts of colocation capacity under billing as of Sept. 30, up from 395 megawatts at the end of June. AMD’s 110-megawatt lease compares with that larger existing billing base.
That 485-megawatt capacity represented more than $700 million in average annualized colocation revenue under generally accepted accounting principles. The new lease gives the Texas project a defined capacity commitment within that hosting business.
Colocation generated $215.4 million of the company’s $232.9 million in third-quarter revenue, or about 92%. The business produced about $137 million in the second quarter and $15 million a year earlier.
Bitcoin mining generated 7.5% of third-quarter revenue. The mix makes hosting the company’s dominant revenue source, and the Texas project extends its AI and HPC expansion.
When does the mining exit take effect?
Core Scientific plans to end its own mining operations by Dec. 31, 2026, then focus on artificial intelligence and high-performance computing hosting from 2027. The Nov. 24 construction start precedes that cutoff, while initial AMD delivery follows it.
That sequence places the project across the company’s mining exit and its hosting-focused expansion. TDLR’s entry gives the project a Nov. 24 start, a first-half 2028 initial delivery and a Sept. 4, 2028, completion target.
The $232.5 million acquisition and $1.3 billion project cost frame the scale of the commitment. The business relies on colocation for 92% of third-quarter revenue, so hosting execution now carries the operating strategy.
The next fixed checkpoint is the scheduled Nov. 24 construction start, followed by initial AMD delivery in the first half of 2028 and full completion on Sept. 4, 2028.