Ethereum Sets Hoodi Upgrade for Dec. 15, Advances Glamsterdam Specs
Ethereum's Nov. 26 All Core Devs Consensus meeting advanced Glamsterdam: EIP-8037 ships unchanged, PR 5770 lands, and Hoodi activates Dec. 15 at 19:12 UTC. FOCIL's fate waits until Dec. 10.

Outputs
Hoodi upgrade scheduled for Dec. 15 at 19:12 UTC, epoch 143,616
EIP-8037 ships as specified with no changes despite breakage concerns
PR 5770 adopted; PR 5820 deferred
Previous Oct. 26 test canceled after ChainSecurity warned fee changes could break existing contracts
FOCIL decision deferred to next meeting, expected around Dec. 10
Ethereum core developers finalized specifications for the Glamsterdam upgrade and scheduled the Hoodi testnet activation for Dec. 15 at 19:12 UTC, or epoch 143,616, according to decisions taken at the Nov. 26 All Core Devs Consensus meeting. The timing matters for anyone running infrastructure: client teams are expected to prepare the necessary releases by early next week. That is a compressed window for node operators to coordinate upgrades, though testnet slippage is routine when final commitments land late.
What was decided on the execution layer?
Execution layer teams agreed to ship EIP-8037 exactly as currently specified, without changes. Some developers had raised concerns about potential breakage and the usability of the gas opcode, but the meeting produced a rough consensus to proceed. Rough consensus is the operative phrase here: it signals agreement sufficient to move forward, not the absence of reservations.
The context sharpens the significance. The upgrade's previous Oct. 26 test was canceled after ChainSecurity warned that the fee changes could alter the behavior of existing contracts. Skipping that test date cost roughly seven weeks of calendar time, and the Dec. 15 activation represents the recovery from that delay.
The takeaway: EIP-8037 advances with a documented, unresolved breakage risk that the community has accepted for now.
What changed on the consensus layer?
Developers adopted PR 5770, a solution for builder payload block-hash verification that imports RLP into the consensus layer. PR 5820 was deferred to a later cycle. No timeline accompanied the deferral.
The decision moves serialization logic across layers, an architectural change with maintenance consequences for client implementations even if it appears procedural on the surface.
What remains undecided?
FOCIL's role in the upcoming Heze/Hegota upgrade stayed unresolved. The discussion centered on whether keeping the forced-inclusion feature as a headline priority could compete with efforts to implement post-quantum cryptographic protections. Some participants favored removing FOCIL to concentrate resources on post-quantum development. Others argued both could progress in parallel.
The compromise is procedural: FOCIL retains its current SFI headline status until developers revisit the upgrade's full scope at the next meeting, expected around Dec. 10. Two competing engineering priorities cannot both claim the top slot indefinitely, and that tension is now explicit on the record.
Post-quantum cryptography was also discussed separately. Kevaundray presented a proposal to adopt Keccak-256 as a shared hash function across systems including LeanVM, XMSS and Sphinx. Developers weighed the trade-offs between Keccak and more standardized hash functions; no decision was recorded.
The takeaway: resource allocation, not technical feasibility, is now the binding constraint on Ethereum's censorship-resistance and quantum-readiness work.
What comes next?
The next ACDC meeting is expected to address the complete Heze/Hegota scope, including FOCIL's status and the potential impact on the post-quantum roadmap. Client releases for Hoodi should appear before then, giving node operators days rather than weeks to test against the Dec. 15 activation at epoch 143,616.