Hut 8 Fully Commercializes Beacon Point AI Campus in $26.6 Billion Pivot
Hut 8 signed a second 352 MW lease at Beacon Point, pushing AI contract value to $26.6 billion, and sold about 3,100 Bitcoin to fund $250 million in buybacks.

Outputs
Hut 8 signed a second 352 MW IT lease at Beacon Point, fully commercializing the campus and lifting AI portfolio contract value to about $26.6 billion.
The company sold roughly 954 Bitcoin in Q3 to fund $74.7 million of buybacks, then about 2,148 more coins for $175.3 million of repurchases; authorization rose to $1 billion.
Hut 8 closed a $1.07 billion senior secured revolving credit facility and has 1,330 MW under construction with 3,180 MW in exclusivity.
First River Bend data-hall delivery is targeted for Q2 2027, Beacon Point Phase 1 for Q3 2027 and Phase 2 for Q2 2028.
Hut 8 fully commercialized its Beacon Point AI campus with a second 352-megawatt IT lease, lifting expected aggregate base-term contract value across its AI data-centre portfolio to roughly $26.6 billion, the company said in its November 4 third-quarter results. The update also disclosed that Hut 8 sold approximately 3,100 Bitcoin across two tranches to fund share repurchases, and closed a $1.07 billion senior secured revolving credit facility.
The figures mark a decisive shift for a company long associated with Bitcoin infrastructure. Management now measures the business in megawatts under construction and contracted tenant commitments rather than coins mined. Hut 8 reported 1,330 MW of utility capacity under construction across its major AI projects, alongside 1,300 MW of additional energy capacity entering exclusivity — a category that now totals 3,180 MW.
Exclusivity is a development milestone, not an operating facility. The contracted value, likewise, describes commitments over years rather than realized revenue. Hut 8's timetable sets an initial River Bend data-hall delivery target for the second quarter of 2027, followed by Beacon Point Phase 1 in the third quarter of 2027 and Phase 2 in the second quarter of 2028.
What does the Bitcoin treasury sale signal?
The capital-allocation choices carry as much information as the lease figures. During the quarter, Hut 8 bought back $74.7 million of shares, funded with proceeds from selling approximately 954 Bitcoin. Subsequent to the quarter, it repurchased another $175.3 million of shares through the sale of roughly 2,148 additional coins, and its board raised the repurchase authorization to $1 billion.
Selling Bitcoin to buy back stock reduces treasury exposure to the coin while concentrating each remaining shareholder's proportional interest in the company. Whether that creates value depends on the repurchase price and the long-term performance of the underlying business — the same trade-off any leveraged or asset-funded buyback presents.
The $1.07 billion senior secured revolving credit facility adds balance-sheet flexibility, but committed borrowing capacity is distinct from cash revenue or drawn funds. The financing structure illustrates how AI expansion reaches the balance sheet of listed miners: large construction programs require large facilities before tenants pay a dollar.
Why the delivery dates matter more than the pipeline
A contracted tenant improves the development case, but execution still depends on power availability, construction, testing, financing and customer readiness. The risk profile differs from Bitcoin mining, where machines deploy in stages and production responds directly to network conditions. A missed utility interconnection or delayed data-hall commissioning pushes contracted revenue further out the curve.
The pipeline-to-infrastructure conversion is the metric to watch. Hut 8 has 3,180 MW in exclusivity and 1,330 MW under construction; the gap between those two numbers, and the pace at which it closes, will determine whether the $26.6 billion contract value translates into operating cash flow.
The update also captures a broader change in listed Bitcoin infrastructure businesses. Their market stories increasingly revolve around electricity access and long-term AI customers rather than the size of their Bitcoin treasuries. That shift can produce a steadier revenue profile — but it does not remove the need for disciplined spending or independently verifiable execution.
The near-term test arrives in the second quarter of 2027, when Hut 8 must deliver its first River Bend data hall on schedule and on budget.
via newsbtc.com (Source)