MARA prices $185 million in 8.75% debt to fund Ohio power plant buy

MARA Holdings priced $185 million in 8.75% debt via subsidiary Long Ridge to fund its $1.5 billion Ohio power plant acquisition, after selling 13,597 BTC to repay crypto-backed loans.

Bitcoin miner MARA raises $185 million in debt after selling $1 billion BTC to repay loans
WitnessBitcoin miner MARA raises $185 million in debt after selling $1 billion BTC to repay loansdenfran / pixabay

Outputs

  1. MARA priced $185 million in 8.75% bonds via Long Ridge to fund a ~$1.5 billion acquisition expected to close Nov. 27.

  2. The company sold 13,597 BTC at an average ~$81,039 for $1.1 billion, using $750 million to repay bitcoin-collateralized loans.

  3. Combined Long Ridge debt of $785 million will cost about $68.7 million in annual interest.

  4. Long Ridge generated $178.5 million in revenue in the first nine months of 2026 with a $3.5 million net loss.

  5. The asset is a 485-megawatt gas plant in Hannibal, Ohio, on 1,600-plus acres slated for an AI computing campus.

Bitcoin miner MARA Holdings has priced $185 million in new debt at an 8.75% interest rate through its subsidiary Long Ridge, financing a roughly $1.5 billion acquisition of an Ohio power plant. The disclosure came late Tuesday, one week after the company revealed it had sold $1.1 billion in bitcoin to repay loans backed by its cryptocurrency holdings.

The transaction, which includes existing debt, is expected to close on Nov. 27. Long Ridge will issue the new bonds to help finance the acquisition of Long Ridge Energy & Power, a 485-megawatt natural-gas power plant in Hannibal, Ohio, sitting on more than 1,600 acres that MARA intends to develop into a computing campus for artificial intelligence customers.

MARA shares rose about 4.7% to $6.72 in premarket trading on Wednesday, recovering part of Tuesday's 3.3% decline to $6.42. The stock remains down roughly 12.5% since Nov. 10, as falling bitcoin prices and the company's pivot toward AI infrastructure weigh on its outlook.

What does the new debt change for MARA's balance sheet?

The structure matters as much as the size. Long Ridge already carries $600 million in notes at the same 8.75% coupon. Once the additional borrowing closes, annual interest payments on the combined $785 million of debt will reach approximately $68.7 million — roughly $5.7 million per month. The new tranche alone adds about $16.2 million in annual interest expense.

That is a fixed, contractual obligation now secured against the power business rather than the bitcoin treasury. It converts a volatile, collateralized crypto liability into conventional project-style financing tied to a physical asset with contracted cash flows.

The plant itself brings revenue. Financial statements filed Monday show Long Ridge generated $178.5 million in revenue during the first nine months of 2026 while recording a $3.5 million net loss. MARA previously estimated the asset's annualized adjusted earnings at $144 million, based on the second half of 2025.

Set against the $68.7 million combined interest bill, that $144 million figure implies meaningful coverage headroom — but the margin depends on the plant sustaining performance through the integration period.

Why MARA sold 13,597 bitcoin

The debt pricing follows a sharp change in MARA's approach to its bitcoin reserves. The company sold 13,597 BTC at an average price of about $81,039 after September, generating $1.1 billion. It directed $750 million of the proceeds to repay loans secured against its bitcoin holdings — facilities that had originally helped finance the Long Ridge acquisition.

The move unwinds the collateralized-loan model that defined the miner's treasury strategy during the last cycle. Instead of holding spot bitcoin financed by borrowing against it, MARA has now monetized a portion of the reserve, cleared the crypto-backed debt, and re-levered against a gas-fired power asset.

The company has also indicated it plans to sell more bitcoin, signaling that the reserve is being treated as an acquisition funding source rather than a permanent hold.

The operational bet behind the financing

The strategic logic runs through the Hannibal site. The 485-megawatt plant and the surrounding 1,600-plus acres give MARA a vertically integrated power position: generation capacity it can either allocate to its own mining fleet or sell to AI compute customers as the campus develops.

MARA has reported interest from prospective large-scale customers for the site. Converting that interest into signed contracts is the next operational milestone — and the one that determines whether the 8.75% coupon on $785 million of notes sits comfortably within the asset's earnings power.

For practitioners, the sequence is the signal: treasury monetization first, deleveraging second, asset-backed refinancing third. Each step reduces exposure to bitcoin price volatility and increases exposure to energy market fundamentals.

The deal is expected to close on Nov. 27, at which point Long Ridge's capital structure — and its interest obligations — become MARA's to service directly.